Case Study - Nokia, London, UK

Project data

  • Customer
  • Nokia
  • Value
  • Confidential
  • Area
  • Confidential
  • Procurement route
  • 2 stage
  • Form of contract
  • JCT 05 Standard Building
  • Programme duration
  • 22 weeks
  • Completion date
  • July 2012
  • Project Manager
  • JLL
  • Architect
  • Gensler
  • Quantity Surveyor
  • EC Harris LLP
  • M&E Engineer
  • PSH Consulting

Overview

Realising the need to consolidate all their staff into one complete office space, ISG began working with Nokia on their new Paddington Central premises from preconstruction stage. Spanning 18 weeks, this project entailed the Cat B fit-out of a 60,000 sq ft commercial office space from the initial development Cat A standard.

Nokia_Band image

The project

This exciting, high-profile project included the fit out of meeting rooms, executive office space and open plan areas. With over 60,000 sq ft of new office space, high-level planning was integral to the successful delivery of this project.

From the initial brief with the customer, ISG developed a detailed programme that co-ordinated all aspects of the move and ensured alignment with Health & Safety regulations. ISG was fully responsible for organising and co-ordinating everything from delivery all the way through to installation and final snagging of the furniture installation.

This proved to be highly successful and the client was delighted with the completed solution offered by ISG.