Case Study - Olympic Overlay works, UK

Project data

  • Customer
  • LOCOG
  • Value
  • £300m +
  • Area
  • 120 sites/venues
  • Completion date
  • December 2012

Overview

ISG's Olympic journey began in 2009 with the construction of the London 2012 Velodrome and led to the creation of the £300 million + ‘event architecture’ for the ‘greatest show on earth’ with the biggest Overlay project in the history of the Olympic Games.

As the only construction company to work on Olympic venues right across the UK, ISG delivered a six-month build programme in just over four months. The team accomplished the incredible: award-winning facilities, ahead of programme, on budget and providing a spectacular backdrop to London’s glorious and unforgettable summer of sport.

Ultimately it was an amazing showcase for ISG’s unique skills, not simply ‘builders’ but sharing the customer’s vision; understanding, planning and being flexible enough to do whatever it took to deliver a successful project.

Olympic case study (PDF)
Olympic Overlay

See how ISG managed the overlay of Riverbank Arena for the 2012 London Olympics

Project deliverables

  • Design and construction of the London 2012 Velodrome 
  • Temporary site works – infrastructure and civil engineering to form the basis for venues 
  • Fit-out of temporary venues – including 700 rooms at the Stadium alone 
  • Non-competition warm-up and training venues 
  • Containment – 200T at the Stadium 
  • Tents – the largest being the Athletes’ Dining Tent, which was the size of three football pitches 
  • Temporary buildings / back-of-house facilities – including the installation of 200,000 temporary seats and the Media Village, home to 20,000 broadcasters and journalists 
  • Hospitality facilities – catering for 4.6 million spectators on-park 
  • Temporary services – water, power, waste management, HVAC and lighting

The added value

ISG quite literally topped and tailed the Olympic spectacular, from creating the infrastructure for the memorable opening and closing ceremonies, to managing wayfinding signage, timing and scoreboards, and transforming venues between events. ISG provided a 24-hour response crew throughout the Games and, post-event, ensured that Lord’s Cricket Ground was ready for a test match just 13 days after it hosted the Olympic archery.

ISG surpassed targets for health and safety performance and sustainability, and delivered a complex package of high quality construction works on time and within budget. This success has been recognised globally, with London 2012 a winner in 7 out of 11 categories at the International Sports Events Management Awards, including Event Overlay & Facilities.

Overlay works at the London 2012 Olympic BMX track

Lee Valley White Water Centre

See ISG's role in the construction of Lee Valley White Water Centre.

Media Centre

The Media Centre housed 20k broadcasters, photographers & journalists - see our role in managing the overlay of the Media Centre for the 2012 London Olympics.

Common Domain

Watch how we managed the construction & logistics in the common domain areas.