‘Completing the circle’ at The O2

28 August 2017

The O2 - ISG

Work is progressing well at The O2 in London, as outlined in new time-lapse footage which has been published on ISG’s YouTube channel.

ISG is ‘completing the circle’ at the iconic London retail and entertainment venue, transforming the remaining undeveloped section under the iconic white dome into a designer £69m outlet village.

The space will provide over 80 new retail outlets with a combined area of circa 400,000 sq ft.

It will finally complete a 360-degree visitor experience at The O2.

The team recently completed the ground floor slab for two of the buildings.

In July, a substantial 430 cubic metres of concrete was poured on site in one day.

The project is set for completion in Autumn 2018.

Watch how the project is progressing in our time-lapse video.